Envisioning - Vision/Scope Approved Milestone
The vision/scope approved milestone culminates the envisioning phase. At
this point, the project team and the customer have agreed on the overall
direction for the project, as well as which features the solution will
and will not include, and a general timetable for delivery.
The deliverables for the envisioning phase are:
- Vision/scope document
- Risk assessment document
- Project structure document
Planning - Project Plans Approved
At the project plans approved milestone, the project team and key project
stakeholders agree that interim milestones have been met, that due dates
are realistic, that project roles and responsibilities are well defined,
and that mechanisms are in place for addressing areas of project risk.
The functional specifications, master project plan, and master project
schedule provide the basis for making future trade-off decisions.
After the team approves the specifications, plans, and schedules, the
documents become the project baseline. The baseline takes into account
the various decisions that are reached by consensus by applying the
three project planning variables: resources, schedule, and features.
After the baseline is completed and approved, the team transitions to
the developing phase.
After the team defines a baseline, it is placed under change control. This
does not mean that all decisions reached in the planning phase are
final. But it does mean that as work progresses in the developing phase,
the team should review and approve any suggested changes to the
baseline.
For organizations using MOF, the team submits a Request for Change (RFC) to
IT operations at this milestone.
The following deliverables are produced during the planning phase:
- Functional specification
- Risk management plan
- Master project plan and master project schedule
Developing - Scope Complete Milestone
The developing phase culminates in the scope complete milestone. At this
milestone, all features are complete and the solution is ready for
external testing and stabilization. This milestone is the opportunity
for customers and users, operations and support personnel, and key
project stakeholders to evaluate the solution and identify any remaining
issues that must be addressed before the solution is released.
The deliverables of the developing phase are:
- Source code and executables
- Installation scripts and configuration settings for deployment
- Frozen functional specification
- Performance support elements
- Test specifications and test cases
Stabilizing - Release Readiness Milestone
The release readiness milestone occurs at the point when the team has
addressed all outstanding issues and has released the solution or placed
it in service. At the release milestone, responsibility for ongoing
management and support of the solution officially transfers from the
project team to the operations and support teams.
The deliverables of the stabilizing phase are:
- Golden release
- Release notes
- Performance support elements
- Test results and testing tools
- Source code and executables
- Project documents
- Milestone review
Deployment - Complete Milestone
The deployment complete milestone culminates the deploying phase. By this
time, the deployed solution should be providing the expected business
value to the customer and the team should have effectively terminated
the processes and activities it employed to reach this goal.
The customer must agree that the team has met its objectives before it can
declare the solution to be in production and close out the project. This
requires a stable solution, as well as clearly stated success criteria.
In order for the solution to be considered stable, appropriate
operations and support systems must be in place.
Deliverables include:
- Operation and support information systems
- Procedures and processes
- Knowledge base, reports, logbooks
- Documentation repository for all versions of documents, load sets, and code developed during the project
- Project close-out report
- Final versions of all project documents
- Customer/user satisfaction data
- Definition of next steps
|